1. Slope/Retaining Walls
  2. Site Safety and
    Construction Matters
  3. Plot Ratio & Site Coverage/Exemption of GFA
  4. Submission of GBP
  5. GI Works
  6. Foundation
  7. Excavation and Lateral Support
  8. Demolition
  9. Superstructure
  10. Service Lanes, Roads and Streets
  11. Occupation Permit
  12. Performance Review
  13. Site Formation Works
  14. Drainage Works
  15. Geotechnical

 

  1. DDO/Disabled
  2. Fire Safety
  3. Excavation Permit
  4. Submission of Plans
    (Other than GBP)
  5. Architectural Design
  6. Restaurant
  7. Hotel
  8. Child Care Centre
  9. Schedule Areas
  10. Consent Application
  11. Cinemas
  12. Hoarding
  13. Qualified Supervision
  14. EPD / Environmental


 

 

01
Slope/Retaining Walls

PNAP 142
- Retaining walls

 

PNAP 166
- GEOGUIDE 1
- Guide to retaining wall design

PNAP 168
- Registration of slopes and retaining walls
- Green hatched black areas in land title documents

PNAP 187
-Keeping buried services out of slopes

PNAP 234
- Geotechnical manual for slopes

 

 

Top

 

02
Site Safety and Construction Matters

PNAP 170
- Metal refuse chutes at construction sites are not recommended

PNAP 176
- Use of plastic sheet to cover scaffolding outside building

PNAP 178
- Control of blasting

PNAP 181
-Temporary wall-supported platforms inside lift shafts

PNAP 209
- Maintenance and replacement works of lift installations

PNAP 224
-Measure for safety for superstructure work
PNAP 232
- Precautionary measures for construction sites


PNAP 255
- Concrete batching plant

PNAP 273
- Contractor's sheds
- Over 2 storeys or above
- Area exceeds 230 m2
- AP and RSE to sign Form BA 18

 

 

Top

03
Plot Ratio & Site Coverage/Exemption of GFA

PNAP 13
- Countable and non-countable GFA including curtain wall

PNAP 68
- Site coverage definition, projection

PNAP 116
-Amenity features

PNAP 207
- Lift shaft area exemption

PNAP 229
- 5% of domestic GFA for recreation use to be exempted
PNAP 230
- Exemption of duct area
PNAP 233
- Dedication

Top

04
Submission of GBP

PNAP40
- Priority submission

PNAP 47
-contravention to Country Parks Ordinance Cap 208

PNAP 48
- Approval and consent procedure for oil storage installations

PNAP 100
- Sanitary fitments calculation in industrial building
- Flatted factory, 1:1 M:F 4.5 sq.m. per person
- Kitchen in restaurant, 2:1 M:F 4.5 sq.m. per person

PNAP 143
- Payment of fee; Buildings without accountable GFA

PNAP 159
- Specified forms

 

Top

05
GI Works

PNAP 132
- GI Procedure
- Qualify supervision

PNAP 225
-Approval and consent procedure for GI Works in scheduled areas

PNAP 244
- GI works as specialized works

 

 

Top

06
Foundation

PNAP 66
- Recognized types of foundation
- Submission of foundation plan
- GI works
- Pre-drilling
- Construction of foundation
- Proof drilling, core drilling
- Form BA 14
- Piling record plan
- An assessment report
- Proof tests
- On site tests

 

PNAP 74
- Dewatering in foundation

PNAP 141
- Foundation design

 

PNAP 161
-Foundation plan in schedule areas 2 and 4

PNAP 242
- Quality supervision plan for foundation works
- Signed by RSC and RSE
- AP no need to sign

 

 

Top

07
Excavation and Lateral Supports

PNAP 74
-dewatering in excavation

 

PNAP 148
-Requirement and procedure for ELS submission

Top

08
Demolition

PNAP 71
-Procedure approval and consent
-Precautionary and protective measures

Top

09
Superstructure

PNAP 121
-Structural design information

- Sampling and testing of steel reinforcement

 

PNAP 187

- Insitu core testing

PNAP 227
- Suspended slabs on new reclaimed land

 

PNAP 249
- Structural requirements for A&A works in existing buildings

PNAP 256
- Structural plans for curtain walls, window walls and cladding

 

 

Top

10
Service Lanes, Roads and Streets

PNAP 26
- Streets for site classification

PNAP 49
- Street improvement plan cannot be regarded as providing a basis upon which a property owner can claim for compensation or damages

 

PNAP 70
- Street widening
- Bonus plot ratio and site coverage
- Set back area to be counted as site area

 

PNAP 92
- Bridges inside or wholly outside and private lot

PNAP 107
- Bridges on private lot (wholly or partly)

 

PNAP 118
- Transfer of plot ratio

PNAP 179
- Cases which service lane may be counted for site area for site coverage and plot ratio

 

 

Top

 

11
Occupation Permit

PNAP 53
- Final amendment to be separated from OP application

PNAP 84
- Lift & escalator installations
- Permanent electricity supply has been completed

 

PNAP 87
- Permanent water supply to FSI before OP

PNAP 188
- Refusal procedure vs pre-mature application

 

Top

 

12
Performance Review

 

PNAP 246
- Performance review

Top

13
Site Formation Works

PNAP 55
- Site formation works for temporary or permanent filling for preventing from flow-slides of loosely placed, un-retained earth fill

PNAP 147
- Exception of site formation work in exempted building works in the NT

 

PNAP 200
- Submission of site formation proposals

 

Top

14
Drainage Works

PNAP 137
- Horizontal drains

PNAP 157
- Drain test

 

PNAP 211
- Maintenance of common drains to be in the common area of the development

 

PNAP 230
- Water seepage

PNAP 238
- Proper disposal system for the drainage of the condensation as part of the drainage system of a building

 

PNAP 248
- Water seepage of aluminium windows

Top

15
Geotechnical

PNAP 78
- Geotechnical Assessment Report
- Criteria for submission of geotechnical assessment

Top

16
DDO/Disabled

PNAP 112
- Exemption from B(P)R 72

 

Top

17
Fire Safety

PNAP 212
- Calculation floor area of prescribed commercial premises

PNAP 231
- FRC for kitchens in restaurants UFS > 45 sq.m.

 

Top

18
Excavation Permit

PNAP 197
- Excavation permit on public roads

 

Top

19
Submission of Plans (Other than GBP)

 

PNAP 66
- Foundation

PNAP 125
- No retrospective approval for UBW /Unauthorized A&A works

 

PNAP 133
- Submission for temporary buildings

PNAP 139
- Supply RGBS & RSC
- Approved plan
- Structural details
- Supervision plan

 

PNAP 190
- Minor amendments

 

PNAP 213
- Sale office submission
PNAP 214
- Contractor registration system

PNAP 215
- Fast track procedures for consent application

 

PNAP 223
- Exemption of podium height restriction

 

PNAP 245
- Exemption from certain sanitary fitments not to be installed

PNAP 250
- Minor amendments to approved development proposals

 

PNAP 272
- Building approval process
- BD administration

Top

 

20
Architectural Design

PNAP 25
- Transformer room
- Access
- Door

 

PNAP 82
- Room seated gas water heater

PNAP 84
- Lift and escalator installations

 

PNAP 98
- Refuse storage and collection

PNAP 106
- Curtain wall system

 

PNAP 114
- Asbestos

PNAP 156
- Lightning protection for buildings

 

PNAP 169
- Natural lighting to staircase

PNAP 173
- Cantilevered projecting structures

 

PNAP 201
- TBE room

PNAP 219
- Lighting and ventilation for bathrooms exemption

 

PNAP 220
- Flushing volume for flushing cisterns

PNAP 222
- Glass reinforced polyester 8 sq.m. 2m
- indoor 4 sq.m. 1.2 m

 

PNAP 235
- Protective barriers

PNAP 236
- Car parks and loading and unloading facilities

 

PNAP 239
- Window and window wall

PNAP 241
- Lighting and ventilation for habitation, office and kitchen

 

PNAP 248
- Aluminium windows

PNAP 258
- Sky garden as refuge floor

 

 

PNAP 266
- 150 mm level difference for external ground level or flat roof

 

 

Top

 

21
Restaurant

PNAP 117

PNAP 231

Top

22
Hotel

PNAP 111
- Hotel concession


Top

23
Child Care Centre

PNAP 117

Top

24
Schedule Areas

PNAP 77
- Scheduled area no. 3
- MTR protection area
- 30m requirement from outer surface of MTR structure
- 5m clear from MTR vent shaft

 

PNAP 85
- Scheduled area no.1
- Mid level
- Various requirements for submissions

PNAP 161
- Schedule areas 2 and 4
- NTNW and Ma On Shan
- Special geological conditions

 

PNAP 137
- Horizontal drains in schedule area no.1

PNAP 165
- Schedule area 5
- Sewage tunnel protection area

 

 

 

 

 

Top

25
Consent Application

PNAP 11
- Consent rejected for plans approved more than two years waived

PNAP 66
- Concurrent processing of applications for foundation excavation

Top

26
Cinemas

PNAP 54
- Requirements for cinemas

Top

27
Hoarding

PNAP 75
- Procedure for application of hoarding
- Requirements for hoarding

Top

28
Qualified Supervision

PNAP 83
- Qualified supervision for building works with significant geotechnical content

PNAP 131
- Qualified supervision to be provided at certain stages of construction or for some particular operations

Top

29
EPD / Environmental

PNAP 124
- Pollution from industrial buildings

PNAP 155
- Marine disposal of mud and dumping of material with the intention of forming reclamation

PNAP 172
- Building (Energy Efficiency) Regulation
- OTTV requirement

 

PNAP 228
- Noise from pump room and ventilation system

PNAP 243
- Construction and demolition waste

 

PNAP 252
- Disposal of dredged/excavated sediment

PNAP 267
- Tree falling

 

PNAP 270
- Landscape treatment and bio-engineering to slope

Top